| Bosen Enerji - Bursa, Turkey |
Boiler type: SteamGen™ 8
|
| Steam data: 43 t/h, 54 bar, 425 °C |
IIn September 2004 Aalborg Engineering signed a contract with Bosen Enerji to supply a new HRSG for Bosen Enerji's power plant in Bursa, Turkey.
The contract covers design, procurement, production, erection and commissioning of a dual-pressure HRSG.
All equipment is purchased in various countries by Aalborg Engineering and the erection work is carried out by a subcontracted Turkish company.
Project data:
| Client: |
Bosen Enerji
|
| Location: |
Bursa, Turkey
|
Year of commisioning:
|
2005 |
| Gasturbine: |
GE LM6000
|
| Boiler: |
SteamGen™ 8
|
| HP Steam capacity: |
43 t/h
|
| HP Steam pressure: |
54 bar |
| HP Steam temperature: |
425 °C |
| LP steam capacity: |
16.5 t/h
|
| LP steam pressure: |
3 bar
|
| LP steam temperature: |
220 °C
|
Scope of supply
- Natural circulation, dual-pressure HRSG
- Steel structure, platforms and stairways
- Flue gas duct and stack
- Boiler feed pumps
- Steam system
- Steam turbine bypass PRDS
- Drain, vent and blowdown system
- Chemical dosing system
- Water & steam sampling and analysis system
- Valves and instrumentation
- Instrument cable installation
- Electrical trace heating
- Motor control centre
- Erection
- Commissioning