KAM - CCPP Thermatel
KAM_CCPP_Thermatel
Kraftanlagen München GmbH - CCPP Thermatel, Monthey Switzerland
Boiler type: SteamGen™ 8
Steam data: 86 t/h, 64 bar, 525 °C

 

In August 2007 Aalborg Engineering was awarded a contract by Kraftanlagen München GmbH to supply the HRSG for a combined cycle power plant being build by Monthel SA at Monthey in the Canton of Valais in Switzerland. The plant will be supplying steam and electricity for chemical companies in the area.

The contract covers design, procurement, production, erection and commissioning of a dual-pressure HRSG with supplementary firing and a selective catalytic reduction (SCR) deNOx system.

All equipment is purchased by Aalborg Engineering and the erection work is carried out by a subcontracted company.

Project data:

Client: Kraftanlagen München GmbH
End User: Monthel SA
Location: Monthey, Switzerland
Year of commisioning: 2009
Gasturbine: Siemens SGT-800
Boiler: SteamGen™ 8
HP Steam capacity: 86 t/h
HP Steam pressure: 64 bar
HP Steam temperature: 525 °C
LP steam capacity: 8 t/h
LP steam pressure: 8.5 bar
LP steam temperature: 210 °C

Scope of supply

  • Natural circulation, dual-pressure HRSG
  • Steel structure, platforms and stairways
  • Gas burner and fuel train
  • Flue gas ducts
  • Steam system
  • Drain, vent and blowdown system
  • Chemical dosing system
  • Water & steam sampling system
  • SCR DeNOx system
  • Valves and instrumentation
  • Instrument cable installation
  • Burner management and boiler protection system
  • Emission monitoring system
  • Erection
  • Commissioning

 

Client: